Construction of biomass thermal power plant with a capacity of 6.6 MW
General Information
Potential projects
Biomass
Location
Settlement Yaski, Beliaevskyi region
Region Odesa oblast
Total capacity
electrical, kWt
Stages
6600 Kwt
heat, kWT
Stages
Kwt
The Name of a Project's Promoter (enterprise/organization)
The Name of a Project's Promoter (enterprise/organization) Limited Liability Company «BILYAEVKA ECO GENERATION» 13-a Myru str., Troitske, Bilyaevka district, Odesa region, 67641; tel: +380 44 483 26 43 e-mail: beg67641@gmail.com
The Type of promoter Commercial project
Contact details Vadym Vovk, Project Manager, tel. +38(097)905-99-73; e-mail: vovkvadim1983@gmail.com
Project details
The current stage of project development Under development
Project description The project plans to construct a thermal power plant (TPP) for 6.6 MW/hour electricity generation with its further sale at the feed-in tariff. The fuel for the TPP will be dry reeds which will be used as a fuel for the TPP to generate steam and then electricity. To ensure the electricity generation of 6.6 MW/hour, 50 thousand tons of reeds per year will be required for continuous work during 350 days for 2500HP boiler, manufactured by “Hurst Boiler & Welding Co. Inc.”. The secondary product produced by TPP will be organic ash, which will be sold as fertilizer. The project plans that the TPP will operate 350 days a year. 15 days – scheduled preventive maintenance (SPM)
Available documentation business plant; land plot lease for 49 years
Total investment
Euro 20729800 €
General Information
Expenditure on construction of additional infrastructure There is a need to build a new 10 kV line (about 800 m). It is planned to build a new transformer substation for 6.6 MW, 10/35 kV. The construction site is located near the Bilyaivka-Yaski highway and does not require the construction of additional roads
The country of origin of prime equipment United States
Date of filling